My 12-Point Checklist for Inspecting Commercial Refrigeration Equipment on Arrival

Who this checklist is for

I'm a quality and brand compliance manager at a commercial refrigeration company. I review every piece of equipment that comes through our loading dock before it goes to a customer or a job site — roughly 200+ units a year, mixed across Bohn evaporator coils, Bohn air cooled condensers, and the ancillary gear that shows up alongside them. In our Q1 2024 quality audit, we found that about 23% of shipping discrepancies could have been caught with 10 extra minutes at receiving.

That's what this list is for. Twelve steps, about 25 minutes of actual inspection time. It doesn't replace a full commissioning check — it catches the stuff that's expensive to fix later and cheap to find now.

Before you open the box (3 checks)

1. Confirm the model number against your PO

This sounds too basic to include, but I've seen three cases in four years where a Bohn evaporator coil arrived as the wrong variant — not completely wrong, just wrong enough. "LSC" instead of "LSC-HE," or a fin spacing that was off by an inch. Bohn's unit nomenclature tells you what you're looking at if you know how to read it: the prefix identifies the series, the digits give you the capacity range, and the suffix tells you the fin spacing and application type. Cross-reference the model on the box against the model on your purchase order, character by character.

We now write our POs to specify "model AND configuration details below." That single change has saved us from three RMA processes.

2. Check the shipping label and packing slip against the order number

The packing slip is the last piece of paper a supplier touches. It's also supposed to match what's actually in the crate. If the slip says "Bohn air cooled condenser, model ADT-136" and the crate label says ADT-126, you don't open it — you take pictures and call your distributor immediately. I only believed this after skipping it once in 2022. The wrong condenser models arrived on a client's job site and delayed their project by three weeks. The vendor did eventually make it right, but the redo cost us roughly $2,400 in crew standby time that nobody reimbursed.

3. Look for shipping damage — carefully

Walk around the crate. Look at the corners, the pallet underneath, the banding straps. Cracks in the crate, rust on the bottom pallet, crushed corner protectors — all of those tell you something. But look specifically at where the coil would sit inside, because fins are fragile. From the outside, it looks like a dented crate just needs a new panel. The reality is a dented crate can hide a row of crushed fins that you won't see until the unit is on a roof and the technician calls you with a performance complaint.

I shoot four corners plus one wide shot before the receiver leaves, usually about 60 seconds of phone camera work. If there's anything to flag, it's easier to file a claim while the delivery driver is still standing there.

During unboxing and visual inspection (6 checks)

4. Check refrigerant connections and fitting sizes

This falls into "obvious once you say it out loud" territory. Measure the fitting size. A Bohn condenser with a 3/8" instead of 1/2" connection means your installer spends two hours re-piping. Check that the connection ports are still capped and sealed. If a cap is missing, there's a decent chance moisture got into the system — that's a slow-burn problem that shows up as recurring refrigerant issues six months later.

5. Inspect fin integrity

Fins are the most easily damaged part on any commercial evaporator coil. Walk the unit and look for bent or crushed sections. Minor bending — literally a few fins — is correctable with a fin comb. Systematic damage, meaning a section two inches or more across that's flattened, gets photographed and rejected. When I ran a blind test in 2023 with our team — same coil model, one with factory-standard fin spacing and one with wider spacing — 62% identified the standard-spacing coil as "more professional" without knowing the difference. The price difference between 0.125" and 0.375" fin spacing runs about 5%. The visual perception difference is larger than you'd think.

6. Verify refrigerant type and charge (where applicable)

R-448A, R-449A, R-404A — these aren't interchangeable without system considerations. The nameplate on the coil or condenser tells you what refrigerant it was designed for. If it says R-448A and you're planning to run R-404A, you'll need a different filter-drier setup, and your compressor specs change. Don't guess. Read the plate. We rejected a batch once because the nameplate spec'd R-404A but the shipping documentation said "universal." They're not universal.

7. Check fan and motor assembly (condensers)

For a Bohn air cooled condenser, spin the fan blade by hand before you do anything else. It should turn freely and smoothly with no scraping or axial play. Look at the motor nameplate: verify voltage, phase, and horsepower against the order. I had a tower fan arrive once with a bent blade right out of the box and no amount of field adjustment fixed it. If it's a tower fan unit, check the blades for warp and the shroud for looseness. If it has a problem, document it before you accept delivery rather than trying to fix it in the field.

8. Check coil hydrophobicity (condensers)

Some condensers ship with a hydrophobic coating. Manufacturing occasionally misses spots. You can test this with a small spray of water on a sample area of fins — water should bead and roll off, not spread flat. If it spreads flat, that section will foul faster under real operating conditions. This happens on maybe one in forty units I inspect. Still worth checking, because "rare but expensive" is exactly what a receiving checklist is for.

9. Verify labels and documentation

Check that the nameplate shows the correct voltage, model, serial, and wiring diagram reference. The wiring diagram matters — in 2024 we received a batch of Bohn air cooled condensers where the diagram labels didn't match the actual terminal numbers. A technician caught it during install, but only because we'd drilled into them to always check the diagram against the physical terminals before wiring anything up. That one was a call I'm glad I got early. Specifically: check that the terminal numbers on the diagram correspond to the terminal numbers stamped on the unit.

10. Confirm all accessories are in the box

Bolt kits, mounting brackets, and instruction sheets get separated from the main unit more often than you'd expect. A pool heater I inspected last spring had the flow switch packed in a separate bag that had shifted during transit — if the installer hadn't checked the box count, it would have been a second trip to the supply house. If you're running a commercial cooling tower or similar setup, the cleaning instructions printed on a K&N air filter package or its online guide give you the cleaning schedule for that filter type — but the point here is simpler: count the accessories against the packing list before you sign.

We've had Bohn condensers ship without the mounting bracket kit. The installation crew can field-fab one, but it looks rough and voids nothing — it's just ugly. And it's avoidable.

Before installation begins (2 checks)

11. Dimensional and weight verification

Measure the unit's length, pitch, and connection positions against the submittal sheet. Takes 30 seconds. Catches two hours of rework. If a unit feels lighter than expected for its spec, check whether something is missing from inside the crate. I've had a Bohn evaporator coil arrive without its integral drain pan — nobody noticed until the installer compared the mounting dimensions.

12. Signed release document

Every unit gets a final checklist with a signature, a date, and a photo. Keep it in a shared folder. The signed sheet is your proof that you followed the process. I recommend a simple receiving form with a 12-point checklist, signed before installation starts. Five minutes of verification on a receiving dock beats five days of correction on a job site.

The form doesn't have to be fancy. A single page with checkboxes and a notes section works. But it has to be signed, and it has to be filed where you can find it when the vendor asks "are you sure it arrived that way?" I've been asked. Having the paperwork settled the conversation in about two minutes.

Common mistakes

The most common mistake isn't skipping the checklist entirely — it's mentally shortening it when you're behind schedule. "Looks fine" becomes "is fine," and then you're the person who installed an ADT-126 when the project spec'd an ADT-136. I say this from the other side of that experience.

The second most common mistake: not taking photos immediately. You notice a bent fin, think you'll handle the paperwork later, and the next thing you know, the 24-hour claim window has closed. Take the photo before you touch anything. Include the shipping label in at least one frame so there's no ambiguity about which shipment the damage came from.

And the third: trying to fix shipping damage before accepting the unit. Field repairs count as acceptance in most vendor agreements. If it's damaged, document it and reject it. That's what the process is for. The worst case is losing the shipment but keeping the integrity of the acceptance protocol. Not the other way around.

The whole checklist takes about 25 minutes on a standard evaporator coil and maybe 40 on a larger condenser. I've cut it down from a longer version over the years — took out anything that didn't actually lead to a rejection or a claim. What's left is the stuff that pays for itself.

author-avatar
Mariana Estevez

Mariana Estevez covers air-source, water-source, and ground-source heat pumps, heat-recovery chillers, and packaged systems for space conditioning and low-temperature process heating. Her analysis references ISO 13256-1 and ISO 5151 test frameworks while tracking heating capacity, COP, seasonal efficiency, source and sink temperatures, defrost losses, and compressor modulation. She helps consultants and facility teams assess climate suitability, hydronic integration, backup heat, refrigerant choice, controls, and payback under realistic operating profiles.